Grey Water Network Handover to Azraq camp WASH Committees

After the completion of the grey water network in Village 3 of Azraq camp, ACTED handed over the infrastructure to the community-elected WASH committees.

On the 28th of February, ACTED celebrated the completion of the grey water network in Village 3 of Azraq camp by organizing an event to hand over the network to the WASH committees and thank all the Syrian refugee Incentive-Based Volunteers (IBVs) involved in the project. ACTED provided meals to all the attendees to event to celebrate together the success of the project supported by OCHA and UNICEF.

ACTED staff thanking the IBVs for all their hard work in the grey water network construction
ACTED staff thanking the IBVs for all their hard work in the grey water network construction

The 19 WASH committees representatives of Village 3 received the toolboxes for the maintenance of the grey water network. In addition, ACTED distributed to all beneficiary households plungers for basic maintenance and unclogging.

The construction works of the grey water network took place between 20th November 2017 and 8th February 2018 with the help of 140 Incentive-Based Volunteers . Thanks to this infrastructure, now over 9,000 Syrian refugees living in Village 3 of Azraq camp have access to a safe disposal mechanism for grey water produced inside their shelters which leads to a cleaner and healthier environment.

Grey water represents all the waste water produced at household level excluding black water from toilets. Grey water might result from handwashing, showering, washing the dishes or clothes.

 Syrian IBVs recruited by ACTED working at the grey water network  
Syrian IBVs recruited by ACTED working at the grey water network

 
Syrian IBVs recruited by ACTED working at the grey water network